Campus Network Modernization

From Mission to Action & Results

ETS Mission

Modernizing Howard University IT through secure, innovative and collaborative solutions to enable the University to accomplish its mission. 

The Network Modernization Project aligns with Howard University’s and ETS’ forward thinking, planning and executing to ensure that the institution continues to thrive, supported by a robust, modern, reliable and secure network infrastructure.

Project Purpose

The Campus Network Modernization project is geared towards enhancing and modernizing the network infrastructure, to ensure we meet the highest connectivity, security, and efficiency standards globally. Howard is partnering with Cisco and taking the bold step to modernize the network infrastructure by replacing the existing wireless network access points and switches with new models to streamline and modernize network operations ultimately improving the student experience. This is a momentous leap forward in the university’s commitment to innovation and excellence in education.

campus network modernization chart
This upgrade will enhance learning, research, and daily operations for students, faculty, and staff.

The Campus Network Modernization project is geared towards enhancing and modernizing the network infrastructure, to ensure we meet the highest connectivity, security, and efficiency standards globally. 

Partnership

Howard is partnering with Cisco and taking the bold step to modernize the network infrastructure by replacing the existing wireless network access points and switches with new models to streamline and modernize network operations ultimately improving the student experience. This is a momentous leap forward in the university’s commitment to innovation and excellence in education.

cisco upgrade technology

Cisco IOS XE: Operating system for the ever-evolving intent-based network.

Project Status: On Track

Updates:

  • Phase III upgrades are complete. Phase IV upgrades are at 85% completion. The Net Ops team is preparing to transform Burr Gym Annex in the coming week, based on stakeholder availability.
  • ETS will begin the RMA process for all legacy equipment collected in phase III & IV
  • UGL wi-fi optimization work will continue with the implementation team across campus.
  • Sec Ops has finalized the security reviews in all buildings in phases I-IV.
  • The Infrastructure and Security team are preparing for the Quality Phase of the Campus Modernization Project. This will include network testing.
  • A final lessons learned will be conducted and published at the conclusion of this project.
  • Schools currently waiting to be relocated will be upgraded during their move.

 

Upcoming Building InstallationInstallation DateStatus
Cook HallDec 14 — Jan 10Complete
Drew HalDec 14 — Jan 10Complete
West TowersDec 14 — Jan 10Complete
East TowersDec 14 — Jan 10Complete
College Hall NorthDec 14 — Jan 10Complete
Bethune Hall AnnexDec 14 — Jan 10Complete
Wheatley HallDec 14 — Jan 10Complete
BaldwinDec 14 — Jan 10Complete
Crandall HallDec 14 — Jan 10Complete
Truth HallDec 14 — Jan 10Complete
Frazier HallDec 14 — Jan 10Complete
BookstoreDec 14 — Jan 10Complete
Academic Support BDec 14 — Jan 10Complete
Dentistry Modular ClassroomsDec 14 — Jan 10Complete
Burr Gym AnnexTBDNot Started

What's Next

Check back for more updates about how this project moves from modernization to optimization.

Updates and Announcements

Check back here for information on:

  • Potential service interruptions and mitigation plans
  • Temporary workarounds for users
  • FAQs on how this might affect devices and access
  • Training and Town Halls